History
The club was originally
organized as a civil defense unit. Early in World War II, small
craft in this area, which could measure up to, certain specifications,
were enrolled under the Transport Controller for use by civil
or military authorities. In 1942, the organization was incorporated
as “Vancouver Island Power Boat Squadrons” with the
threefold purpose of:
- Assisting in time of national or local emergency.
- Fostering interest in the safe and efficient handling of small craft.
- Promoting all matters of interest to small craft operators.
Membership at this stage totaled 350 vessels from 25
to 110 feet long, and the Squadrons undertook patrols in the R.A.F.
Gulf Islands training area, blackout inspections for A.R.P., and
training exercises with Army Reserve Forces.
When the war was ended, a majority of the members voted to perpetuate
the association and added to its objective the functions of a yacht
club. A clubhouse was built at Canoe Cove under a lease arrangements
and late in 1947 the Bylaws were altered and the name changed to “Capital
City Yacht Club.” In October 1957, the club abandoned its situation
at Canoe Cove. Much effort was put forth during 1958 in the search
for and planning of a club-owned site which could be developed as
a club headquarters with clubhouse and mooring facilities. At the
same time, negotiations with Clark Bros. were being held and an agreement
was eventually reached late in 1958 to lease from Clark Bros. in Tsehum
Harbour. A panabode type building was purchased and erected by the
personal efforts of the Club members on Clark Bros. property during
the summer of 1959.
The Clubhouse gave the C.C.Y.C. members the feeling of owning and
with this inspiration, suitable property was located in Blue Heron
Bay, just south of Tsehum Harbour. Negotiations for the purchase of
some two acres were completed in May, 1964. During the next few years
a foreshore lease was applied for and received. Plans to move the
Clubhouse became a fact in the later part of 1966. The 1967 programme
included the dredging of the entrance channel on a cost sharing basis
with the Government of Canada. When this project was completed the
same company continued into Blue Heron Basin where a total of 36,149
cubic yards were extracted. All costs for this were paid for by the
club. A pile driving company was the next step and approximately thirty
piles were driven in the bay. A great deal of praise and credit should
be given to the members, the Ladies’ Auxiliary and the newly
constituted junior members for the work parties, properly organized,
in the building of the floats, wharfs and the grounds surrounding
the area. By April 1st., 1968, 825 ft. of mooring floats and docks
were placed in the water ready for use by the membership.
Between 1968 and 1972 there were boatsheds moved into the newly formed
moorage area. Twelve members worked diligently to design and build
a covered moorage complex, which greatly enhanced the Basin area.
The Ladies’ Auxiliary were working hard during this time planning
and arranging the landscaping of the uplands area. The Ladies’
Auxiliary also paid for the paving of the parking area which was a
very great asset for our Club.
The General Meeting in 1972 approved an overall plan for development
of the Club. This plan was divided into five separate phases and presented
to North Saanich Council in April, 1983, for their approval, which
was granted. This first phase consisted of the extension of our present
Clubhouse. Many meetings followed and then construction began with
the members taking part by way of work parties. All the while the
Clubhouse was being constructed, the plans for the dredging were being
prepared and in June, 1973, ten copies were sent to Ottawa and one
to the Department of Fisheries for their approval. These approvals
were granted in the latter part of June and July, 1973.
This then allowed us to prepare tender documents and call tenders
for the dredging and driving of piles for the wharfs. Tenders were
opened September 6, 1973 with Greenlees Piledriving being the lowest
tender received. The contract was awarded and work proceeded through
the winter and following spring. By June, 1974, the dredging was complete,
piles driven and approximately 600 feet of wharf constructed. During
this winter and spring the Clubhouse was progressing very well and
a final drive of work parties completed the job in time for our Sailpast
in June, 1974. A great deal of credit should go to the Properties
Committee for their hard work and also the Ladies for their donation
of drapes, etc.
The next phase on the foreshore was the construction of the covered
moorage. W. Campbell Ltd. was awarded the contract to design and build
these structures. They were started in late August and completed in
October, 1974. The new units gave us an additional 46 covered berths
and improved the overall appearance of the basin. Erosion along the
Clubhouse and parking lot foreshore eventually necessitated a retaining
wall. Some creosoted piles were donated to the club, and in 1980 a
contract was let to drive them all along the bank. More support proved
necessary and in 1982 a further contract installed cross ties and
anchors. This has produced a solid and durable retaining wall which
has been capped with a cement walkway. The finishing touch is given
by aluminum guard rails to match the new aluminum ramp. In the same
year the grid was extended five feet through the dedicated efforts
of some Club members. Further improvements are intended as popular
use of the gird continues.
During 1984 the Clubhouse was extended by 500 square feet and a new
garage style storage building was installed to the west of the parking
area. B and C docks were rebuilt during 1984, 1985 and 1986. The year
1986 saw major renovations to the Clubhouse heads, a new rear entry
and some renovations to the galley. The seawall was extended in 1987
from the gate west to the Cole property. This was necessary to stabilize
the parking lot in that area and allow for future dredging in the
adjacent channel.
An agreement was reached to purchase the Cole property in 1985, and
this was completed in 1988. Planning an extension to our water lease
was also initiated at the same time. Development plans and related
permits were prepared. Final permits were received in 1988 with plans
for some 37 new berths in our basin. Approval for the related expenditures
was given by the membership at the Annual General Meeting in November,
1988, and a contract was let to install a seawall extension west from
the existing wall in front of the Cole property. This was completed
in the early part of 1989 and dredging was done later in the year.
Construction and installation of E dock was completed in 1990.
The new breakwater was completed in 1991.
1992 - 1993 two new double wide boat sheds were completed.
1994 - Two more double wide boat houses were completed and the electrical
upgrading continued.
1995 - Was a very busy year - 3 additional double wide boat houses
were built, an office was added to the storage shed, C Docks roof
replacement was started, a canopy was built over the entrance to the
club house, the electrical upgrading was completed and the Les Cole
house was renovated.
1996 - A year of Construction and Destruction! During the year three
double wide boat houses were constructed. The main wharf of E Dock
was moved back 15 feet and the fingers were replaced with larger ones.
The fingers were also replaced on BB Dock. New dock lighting was installed
on A, B, and E Docks. The foreshore purchase was concluded with the
exception of final documentation. The seawall repairs were completed
and the balance of the plans were to be started when ---- the “Blizzard
of ‘96” struck. C Dock collapsed under the weight of the
snow and high winds. A and B Docks also lost boat houses. 31 boats
were sunk and dozens of boats damaged. Within hours of the disaster
the Canadian Coast Guard was on the scene along with the crews of
Campbell Construction and Victoria Pile Driving. Our members began
arriving and assisting wherever they were needed. So began the lengthy
and exhausting task of clearing, refloating the boats and rebuilding.
Our Club has a strong tradition of volunteerism and if ever it has
been put to the test, this is it!
1997 - The beginning of the year saw many of our members undertaking
the massive cleanup of both sunken and floating debris. A considerable
amount of aluminum was salvaged for later sale and under the watchful
eye of ex-fire chiefs the balance of the debris was burned. A contract
was let for 37 piles to be driven and 500 feet of dock space for C
wharf. Before building of the boathouses got underway, a fire on B
wharf destroyed 2 boathouses and damaged a third. Two tenders were
called, the first for a 24 double wide and six single boathouses and
the second, to replace the burned boathouses and the damaged one.
Once construction began Members completed all the necessary electrical,
plumbing, locating and connecting the boathouses together with any
other miscellaneous jobs. A sale of bonds within the membership raised
$560,000.00 which together with the insurance proceeds was sufficient
to complete the work. Eleven months to the day the project was completed
and all the berths assigned. Also during the year the membership finished
the seawall improvements, the entry gate building and the installation
of the new ramp. The flag pole was refurbished and relocated and finally
the surrounding area was landscaped. During the next two years our
volunteer workers continued to improve the Club’s facilities.
A second entry gate and house leading to D wharf was constructed.
The balance of the lawn area was regraded and seeded to lawn. During
this period a Fire Protection system consisting of mains, stand pipes,
hose boxes and fire extinguishers were installed on C wharf. Mains
and standpipes were also installed on A & B wharves and initial
installation was begun on D wharf. The Electrical system was completed
and passed a final inspection. As-built drawings of the entire electrical
system were made and are stored on an auto cad disc. At the same time
general maintenance was carried on throughout the property. In the
fall of 1999 the Cole house was repainted and a contract was let for
the repaving of the westerly portion of the parking lot. At the end
of 1999 a second repayment of the bond issue was made leaving a balance
of only $182,000.00 to be carried into the year 2000.
Between the years 2000 and 2004 a number of changes and improvements
have taken place. Repayment of the bonds was completed. The first
lady was appointed to the Directorship and the members agreed by vote
to construct a new clubhouse. Sadly the Ladies Auxiliary was disbanded
and an Auxiliary was formed to include all members. “A”
wharf was rebuilt and four double wide boathouses were added replacing
old ones. The end of B wharf was rebuilt. The complex was split replacing
one half with three double wide boathouses. In all 850 feet of services
and wharves were rebuilt on A and B wharves by volunteer members. In
2007, after a three year period the members of the Auxiliary
unanimously decided to revert back to the name Ladies Auxiliary and
change the bylaws accordingly. The volunteer work crews continued to be
kept busy with a number of projects. The Ladies Auxiliary made a
significant contribution towards replacing the old sign and the
volunteer work crews erected the sign along with supporting structures,
landscaping, street improvements and a new entrance. “D” wharf fingers
were upgraded and a new sewer pumping system station for the Cole house
was completed. Fobs replaced the keys with the installation of a
computer operated security system. After two unsuccessful meetings the
members of the Club finally approved the financing cost of a new
clubhouse. In May 2009 the old clubhouse was demolished and the
construction of a new one began. 2010 will see the completion of the
new clubhouse and the first Lady Fleet Captain in the history of Club.
|